Key Dates

Planning

September 2022 through Spring 2023

Groundbreaking
  • July 2024
Construction Completed

August 2025 (anticipated)

In Progress

Overview

Demolition underway, building on track to start this summer

After some delays in abatement throughout the Golf Acres site in the older buildings, there's noticeable progress as demolition is well underway.

The project is on track for receiving a building permit in early June 2024. This keeps the project--on the current timeline--on track for an August 2025 opening. 

Visit the “photos” tab below for images of the ongoing demolition. 

The team is planning a groundbreaking event for July 2024.